Adani's Tarali project work halted in Satara
The department has ordered all work to stop until approvals from the competent authority and wildlife board are received.
Amid the ongoing global crisis of forest and wildlife conservation, the Maharashtra Forest Department has ordered an immediate halt to the construction of Adani Green Energy's 1,500 MW Tarli pumped storage project in the Patan taluka of Satara district, as per an order. The department stated that the company began construction without the mandatory prior approval from the National Board for Wildlife (NBWL). The company claims it had obtained the necessary approvals for construction and that the proposal for wildlife clearance is still under consideration. There is also an ongoing investigation into two different figures recorded in government documents regarding the project's cost.
Amol Satpute, the Deputy Conservator of Forests in Satara, and R. S. Nalawade, the Forest Range Officer of Patan, have issued show-cause notices to the officials associated with the project. According to the forest department, their inspection revealed that work was ongoing at the site. The department stated that this area falls within the region of the Sahyadri Tiger Reserve, which is considered environmentally sensitive. On this basis, the department had emphasized the necessity of obtaining approval from the National Board for Wildlife before commencing construction. The Indian Express also observed work being carried out at the project site during its visit.
In the order dated November 13, the department has instructed that all work be halted until approval is received from the competent authority and the wildlife board. The company has also been asked to provide a written response in person within three days of receiving the notice. The department wants to know on what basis construction was initiated. It has requested original or certified copies of the project maps, all statutory approval documents, and tree felling permissions. The department has warned of legal action if satisfactory responses and necessary documents are not provided.
The proposed project at the Tarli dam reservoir spans 150.74 hectares of non-forest land in the villages of Nivade, Tondoshi, Kalambe, and Jalu. The estimated cost recorded in a document from the Ministry of Environment dated February 11, 2025, was ₹5,675 crore. The State Wildlife Board had stipulated that 4% of the project cost be deposited for wildlife conservation in the Sahyadri Tiger Reserve. Based on this, M. Srinivas Reddy, the Chief Conservator of Forests (Wildlife) of Maharashtra, had asked the company to deposit ₹227 crore in March 2026.
According to reports, the company had requested to consider ₹56.75 crore as part of the project cost in a notarized affidavit dated September 8, 2026, and Reddy informed that this figure was accepted in a letter dated October 12. Subsequently, the company deposited 1% of the revised amount, i.e., ₹56.75 lakh, into the account of the Tiger Reserve. Thus, the total conservation amount due is ₹2.27 crore. Reddy later told Hindustan Times that the department has not yet accepted the revised estimate and has sought clarification and documents from the company.
The company claims that the figure of ₹56.75 crore is only the cost of the survey and investigation of the site, and the total project cost remains ₹5,675 crore. According to the company, the project is on private, non-forest land and is located 3.2 kilometers away from the Koyna Wildlife Sanctuary. It asserts that no part of the project falls within any notified protected area or notified environmentally sensitive area. The forest department's notice is based on the status of the area that the department considers environmentally sensitive.
In a statement on November 16, the company stated that it received a no-objection certificate related to non-forest land on January 23, 2024, environmental clearance on February 11, 2025, and approval to commence construction on April 7, 2025. The company claims it has submitted a proposal for approval to the National Board for Wildlife based on the total project cost. A decision on that proposal is still pending.
Rohan Bhate, an honorary wildlife warden from Satara, filed a complaint on October 30 on the Prime Minister's grievance portal and Maharashtra's 'Aaple Sarkar' portal, alleging that the project cost has been misrepresented. Following this, the Ministry of Environment directed the state forest department to conduct an expedited investigation on November 6. Congress General Secretary Jairam Ramesh has reiterated the demand for a Joint Parliamentary Committee (JPC) investigation into the Adani group's operations, calling the cost dispute a 'massive scam'. Two questions remain to be answered in the investigation: on what cost the conservation amount will be determined and whether approval from the wildlife board was necessary before commencing construction. It will also be important to see what steps the relevant authorities take to prevent violations of environmental laws in the area and ensure that the law is applied equally to all.