Questions raised over Adani Group’s Maharashtra power contract
Did the bidding conditions give all competitors an equal opportunity?
Following the notice to stop work on the Tarali project, another Adani Group company is in the news for the wrong reasons. A long-term contract for round-the-clock power supply in Maharashtra has raised questions about the terms of government procurement and fair competition. Under the arrangement through which the State power distribution company MSEDCL has contracted to buy 2,500 MW of power, one Adani Group company will use solar power from another company in the same group. The controversy is not only about the ownership of the two companies, but also about whether the bidding conditions gave all competitors an equal opportunity.
MSEDCL’s bid document provides for the supply of 2,500 MW round-the-clock (RTC) power for 25 years. At least 51 per cent of the power each year must come from green sources whose origin can be verified. The remaining supply can be met through alternative sources. It would therefore be inaccurate to call this a contract for 100 per cent renewable power.
The purpose of an RTC arrangement is not to supply electricity only when solar or wind energy is available, but to ensure a regular supply using different sources and storage as required. The cost and responsibilities for solar power generated during the day and power available at night or during peak demand are not the same. Any agreement must be assessed not only by its price but also by its availability conditions.
A key provision in this tender concerned solar power already under contract. According to the document, MSEDCL had entered into an agreement on October 29, 2024, with Adani Renewable Energy Fifty-Five Limited to buy 5,000 MW of solar power. This power was to be made available to the successful bidder for the new RTC contract. The bidder was to manage this solar supply while meeting its obligation to provide the agreed RTC supply.
It is also important to clarify the corporate structure of the contract. According to a stock exchange filing by Adani Energy Solutions dated September 8, 2026, the original allocation was made to Adani Power. It later transferred the related rights and obligations to Powerpulse Trading Solutions Limited. Powerpulse is a wholly owned subsidiary of Adani Energy Solutions. It signed a power purchase agreement with MSEDCL on the same day.
Scroll reported that competing bidders had expressed concern that the Adani Group could benefit from production-related information because the company generating the solar power belonged to the same group. A spokesperson for Adani Power dismissed this concern. The company said objections had been addressed before the bidding through clarifications and that the pre-contracted solar project’s association with Adani did not constitute an unfair advantage.
Price is another important aspect of the matter. The rate under the contract is listed as ₹5.90 per unit in details from energy-sector research organisation JMK Research. According to Scroll, the Maharashtra Electricity Regulatory Commission, while approving the rate, referred to the specific structure of the agreement and the supplier’s responsibilities. The Commission found it favourable compared with some approved thermal power rates. However, the report has raised questions about the cost compared with other RTC procurement options.
It would be wrong to subtract the solar power rate from the rate for the entire RTC package and treat the difference as the company’s profit. According to Scroll, payment for the solar component already purchased is adjusted in the final accounting; simply adding the two rates would also be incorrect. Assessing the actual cost requires looking at additional power, storage, the cost of ensuring supply and the terms of the contract together.

The key question in public procurement is whether all bidders had the same information, adequate time to prepare and an equal opportunity to assess the risks. The participation of companies from the same group in generation and supply does not in itself prove irregularity. But in such a structure, equal access to information and clear documentation of the decision-making process become more important.
For consumers, too, the declared purchase rate alone cannot be the basis for scrutiny. They need to understand the reliability of supply, how additional costs are shared and who is accountable if the terms are not met. Nor is it appropriate to treat this purchase rate as the final rate on household electricity bills. The regulatory evaluation should make clear what benefit the agreement offers the distribution company and consumers compared with the available options.
The Maharashtra government, MSEDCL and the regulator should make public the full basis for competitors’ objections and how they were disposed of. The Adani Group’s position, too, should be examined with the same seriousness; however, under company law, the key question will remain who made these decisions behind the company veil. Confidence in this arrangement will depend not on allegations or assurances, but on evidence of comparative costs, a fair bidding process and actual supply performance.